CAPITAL BUDGETING UNDER UNCERTAINTY


* Alternative approaches to risk adjustment

* Adjust the cash flows to reflect the risk. Be more conservative in estimating cash flows for riskier ventures and less so for safer ventures. The danger of this approach is that:

- The risk adjustment will vary from person to person and from project to project

- There is ample room for preconceptions and biases to alter the adjustment

- Risk may sometimes be double counted (in the cash flows as well as the discount rates).

* Allow the decision maker to factor in the risk, when he (she) makes the decision. For instance, when comparing the NPV of two projects, the decision maker may choose the one with the lower NPV, because he (she) feels it is less risky.

* Do what-if analysis on the cash flows, i.e, what would the NPV be if revenues were 15% greater than or less than expected.

* Adjust the discount rate to reflect the risk.

* Risk adjustment techniques used by respondents
Technique %
No adjustment is made 14
Adjustment is made subjectively 48
Certainty-equivalent method 7
Risk-adjusted discount rate 29
Shortening payback period 7
Others 5

* Sensitivity Analysis

All capital budgeting analyses make assumptions about future revenues, expenses, salvage value, tax rates and the project lifetime. Examining the effects of changing each of these variables individually on the NPV and IRR is sensitivity analysis.

An Example: A Store Analysis for The Home Depot

Base Case Assumptions

Initial Investment in the Store (100,000 squre feet) = $ 12.5 million

Expected Life of the Store = 10 years

Additional Investment needed at the end of year 5 = $ 1 million

Salvage Value of the Store Premises at the end of 10 years = $ 5.5 million

Expected Revenues/Square Foot in first year = $ 300 / square foot

Pre-tax Operating Margin (EBIT/Sales) = 10.00%

Working Capital as a % of Revenues = 10.00%; Investment at beginning of each year and completely salvageable at the end of the project life.

The depreciation each year is computed using ACRS depreciation rates.

The corporate tax rate is 36.00%; The cost of capital is 12.5%

Base Case Analysis 7

Year Investment Revenues EBIT (1-t) Depreciation Chg. in WC FCFF
0 -12500000 -3000000 -15500000
1 30000000 1920000 540000 -150000 2310000
2 31500000 2016000 432000 -157500 2290500
3 33075000 2116800 345600 -165375 2297025
4 34728750 2222640 276480 -173644 2325476
5 -1000000 36465188 2333772 221184 -182326 2372630
6 38288447 2450461 176947 -191442 2435966
7 40202869 2572984 141558 -201014 2513527
8 42213013 2701633 113246 -211065 2603814
9 44323663 2836714 90597 -221618 2705693
10 5500000 46539846 2978550 72478 4653985 13205012

FCFF = EBIT (1-t) + Depreciation + Change in Working Capital

Net Present Value (at cost of capital of 12.5%)= $ 1,067,099 : Accept the Project

Internal Rate of Return = 13.83% > Cost of Capital : Accept the Project

Sensitivity Analysis



A Variant on Sensitivity Analysis: Scenario Analysis

In scenario analysis, specific scenarios are defined, with growth and income characteristics under each. The net present value and internal rates of return for the project are estimated under each scenario ñ



What next?



* Effects Of Assumptions About Project Lifetime



Consider the following project:

Initial Investment = $1,000,000; Salvage Value after 10 years = $200,000

Initial Working Capital Needs = $100,000; Maintain at 25% of Revenues

Revenues in year 1 = $400,000; Grows at 10% a year;

COGS = 50% of Revenues

Discount rate for project = 15%

Year Initial Invest. Revenues COGS BTCF ATCF WC Chg NATCF
0 -1100000
1 400000 200000 200000 120000 0 120000
2 440000 220000 220000 132000 10000 122000
3 484000 242000 242000 145200 11000 134200
4 532400 266200 266200 159720 12100 147620
5 585640 292820 292820 175692 13310 162382
6 644204 322102 322102 193261 14641 178620
7 708624 354312 354312 212587 16105 196482
8 779487 389743 389743 233846 17716 216130
9 857436 428718 428718 257231 19487 237743
10 943179 471590 471590 282954 21436 261518


* Monte Carlo Simulations

Step 1: Instead of using an expected value for each of the inputs, develop probability distributions for each of the variables.


Example: In the Home Depot example, assume the following distributions for each of the following variables ñ

Variable Distribution Expected Value Characteristics of the Distribution

1. Revenues General $ 30 million Value Probability

$ 20 million 0.125

$ 25 million 0.1875

$ 30 million 0.375

$ 35 million 0.1875

$ 40 million 0.125

2. Growth Rate Normal 5.00% Standard Deviation = 2.00%

3. Operating Margin Uniform 10.00% Minimum of 2.50%

Maximum of 20.00%

4. WC as % of Rev. Normal 10.00% Standard Deviation = 2.50%

Estimation Issues:

Step 2: Draw one outcome from each distribution.

Example: In the Home Depot example, assume the following drawings ñ

Variable Drawn Outcome

1. Revenues $ 25 million

2. Growth Rate 6.35%

3. Operating Margin 10.00%

4. WC as % of Rev. 9.16%

Estimation Issues:

Step 3: Estimate a net present value, based upon the outcomes drawn

Example: In the Home Depot example, calculate the net present value based upon the outcomes drawn in step 3.
Net Present Value from simulated outcomes = - $13,423
Internal Rate of Return for simulated outcomes = 12.48%

Estimation Issues:

Step 4: Repeat step 2 and 3 a sufficient number of times.

Example: In the Home Depot example, the simulations were repeated 1000 times. The number was set to a fairly large number because

Estimation Issues:

Step 5: Compute the summary statistics for the net present values across all the simulations (Expected Value, Standard Deviation, Minimum, Maximum, Percent of time under zero) and plot the net present values on a graph.)

Example: In the Home Depot example, calculate the summary statistics for net present value based upon the simulations.
Net Present Value Internal Rate of Return
Expected Value = $ 1,067,150 Expected Value = 13.84%
Standard Deviation = $ 451,335 Standard Deviation = 0.55%

Coeff. of Variation = $ 451,335/1,067,150 CV of IRR = 0.55%/13.84%

Minimum = -$ 9,504,201 Minimum = -1.21%

Maximum = $ 31,013,450 Maximum = 47.95%
% of time below zero = 20.16% % of time below Discount rate= 20.16%


Step 6: Use the distribution of net present values, rather than just the base case net present value to make your decision.

Example: In the Home Depot example, there are a number of questions that can be answered with this simulation, including




* Decision Trees

Stage 1: At t=0, conduct a $500,000 study of market potential.

Stage 2: If it appears that there is a significant market (assumed to have probability 0.8) at t=1, spend $1,000,000 to build a small plant to manufacture prototypes for use in industry.

Stage 3: If the reaction to the prototypes is good, at t=2, build a larger plant for $10,000,000. The project is expected to generate cash flows for four years, before the patent expires.

Assume that the discount rate is 11.5%.

Time Periods



NPV = 0.144* 15,250 + 0.192 * 436 + 0.144 * (14,379) + 0.32 * 1397 + 0.2* (500)

= - $ 338

Note on calculations:

Probability of best case scenario = 0.8 * 0.6 * 0.4 = 0.144

NPV under best case scenario = - 500 - 1000/1.115 - 10,000/1.1152 + 10,000/1.1153 + 10,000/1.1154 + 10,000/1.1155 + 10,000/1.1156 = $15,250

The Abandonment Option

In the example above, assume that you can abandon the project at the end of t=3, if the cashflows turn out to be negative (-2,000).



NPV = 0.144* 15,250 + 0.192 * 436 + 0.144 * (11,176) + 0.32 * 1397 + 0.2* (500)

= $124