The Sandhogs
Larry McCloy,
construction superintendent for The Sandhogs had to make a decision: Should he call
off tomorrow's press conference and shut down construction? Planned to
celebrate the tunnel's having reached the center of the river, the press
conference was to be a major public-relations event. But two engineers had
warned McCloy that predicted flood conditions and
leaking joints in the new tunnel's temporary metal lining might pose danger.
The Situation
The Sandhogs had attained a
nearly legendary reputation for superiority in tunnel construction. In a
business typified by unexpected delays and late completions, the Sandhogs had
finished almost every tunnel on schedule. Even more impressive to people in an
industry where fatal construction accidents are frequent, the Sandhogs had
never had a fatal accident. The Sandhogs attributed their singular record
mainly to the exceptional skills of their foremen, who had earned the
reputation of being able to solve any problem that a construction project could
throw at them. Time and again, the foremen had overcome serious challenges. The
Sandhogs also attributed their excellent record to their careful adherence to
written procedures. They did everything by the book. No tests were omitted, no
details overlooked.
This tunnel was being pushed
through muck in the bed of the
Or, at least the joints were supposed
to be water-tight. The joints had been leaking almost since the project began.
At first there had just been occasional trickles. But the trickles had become
more frequent over time; and a year ago in March and again June, there had been
really serious flows of water that the workers had labeled "gushers."
These gushers had forced The Sandhogs to shut down work and to bring in pumps
until they stopped the flows of water. Each time a leak had occurred, including
the two gushers, The Sandhogs had succeeded in eliminating the leakage by
retightening the bolts that held the TMLs together,
and there seemed to have been no permanent harm.
People had advanced several
theories about this leaking. One theory held that the workers had grown
increasingly careless over time, with the result that they made assembly errors
more and more often. The Sandhogs had tried to address this concern by
emphasizing need for assembled surfaces to be clean and the importance of
testing the tightness of every bolt with a torque wrench.
A second theory held that TMLs didn't have enough bolts holding them together, so the
joints were not stiff enough and the bolts tended to loosen over time. The
Sandhogs tried to address this by increasing the torque level that each bolt
had to meet. Nevertheless, the leakage had not only continued but become more
frequent. Midwest Casting's engineers said that the new torque requirement
might actually be exacerbating the problem by imposing uneven pressures on the
gaskets between TMLs.
A third theory held that the
gaskets didn't have enough resilience. Although laboratory tests said they
exceeded the design specifications, they were a new plastic material rather
than the traditional rubber. Anything new may have unexpected deficiencies.
A fourth theory held that the TMLs were too thin, causing them to flex too much. Two
years ago, when construction started, The Sandhogs were using thicker TMLs. But the engineers at Midwest Casting, the firm
supplying the TMLs, had recommended shifting to a
stronger alloy that could be thinner, lighter, and faster to assemble on site,
thus making it easier to meet the construction schedule. This change might
explain why leakage became more frequent about 16 months ago.
Unfortunately, there was no way
to go back and replace TMLs that were in place if
they were too thin or their gaskets were inadequate or they needed more bolts.
At best, Midwest Casting could change the TML design when they produced the
next batch of TMLs. There were enough TMLs already on site for another five or six months of
work.
A fifth theory laid the blame
on the spring melt. In March a year ago, when the first gusher occurred, one of
the engineers, Roger Bonjovi, speculated that this
gusher was somehow related to the strong river currents or the high water
level. The winter snows had been melting and water levels were high, and this
gusher had erupted about 36 hours after the river level began to rise. However,
the spring-melt theory couldn't account for a second gusher that occurred in
June, after the water levels had receded and the current slowed.
Like Bonjovi,
some of the engineers, both within the Sandhogs and at
A few of Midwest Casting's engineers have
formed an informal task force to redesign the TMLs
and, especially, the joints between TMLs. This task
force has so far come up with 43 design proposals. Laboratory tests on one
design, a so-called capture-lip joint, have demonstrated that it is "a
good thing."
Larry McCloy, The Sandhogs' superintendent of construction,
disagrees with these engineers, both about the risks posed by the leaks and
about the desirability of design changes. McCloy has
concluded that he can accept the occurrence of some leakage and he worries that
design changes might harbor worse problems. Joe Cullister,
Midwest Castings' liaison engineer for the tunnel project, agrees with McCloy. McCloy and Cullister have discussed the leakage with The Sandhogs top
management, who have agreed that the current situation is acceptable. Explains McCloy,
Although leaks have been
frequent, there had been no gushers since last June. None of the leaks, even
the two gushers, caused long-term damage, and we've had no trouble stopping
them. All we've had to do is readjust a few bolts. Our experience shows that
the TML design has enough safety factors to make some joint leakage acceptable.
Since some leakage is
accepted and indeed expected, it is no longer a serious anomaly that we have to
eliminate. Building a tunnel always involves uncertainties. We work on these
projects because we like the challenges they present and we accept the risks
that go with those challenges. If we would try to eliminate every little
anomaly, we'd never complete a tunnel.
The main thing is not to
introduce sudden changes in the way we do things. Abrupt changes escalate the
risks. We need to stick with procedure and to modify procedure only when we are
certain that a change will be an improvement. Since we aren't sure what is
causing these leaks, we can't be sure that a change will be an improvement.
The Decision
Two of The Sandhogs’ engineers,
Roger Bonjovi, and Arnie
Thomas, have gone to see Larry McCloy and told him
that they are recommending that The Sandhogs immediately halt construction on
the tunnel and cancel the press conference scheduled for tomorrow. They
explained that they are deeply concerned about the effects of the record warm
temperatures that have moved in over the northwestern United States and Canada,
extending as far east as the Rocky Mountains. The weather bureau is predicting
that the abnormal warmth will continue for some time, producing a rapid spring
melt with consequent flooding. The
Bonjovi and Thomas reminded McCloy
that the first gusher occurred during the spring melt last year. This year, the
weather forecasters are saying that the record high temperatures are going to
make the water levels and floods much, much worse. If strong river currents
were a factor last year, they are going to be a much bigger factor this year.
Perhaps the strong currents will recarve the river
bottom and subject the tunnel to pressures outside its design parameters. In
fact, if the river really acts up, it could rupture the tunnel. The uncertainties
are too great for The Sandhogs to do more work on the tunnel until the water
levels subside, say three or four weeks from now.
The press conference was
scheduled months ago. The Governors of Oregon and Washington as well as all
four Senators will be in the tunnel, at the construction face, when The
Sandhogs' CEO announces that they have reached the middle of the river. All the
major television stations will be covering the event; they have laid their
cables and set up other equipment inside the tunnel. Because so much equipment
is already inside, it is too late to move the press conference outside the
tunnel, but it will be a public relations disaster if a gusher cuts loose
during the press conference!
After Bonjovi
and Thomas left, McCloy consulted his chief engineer,
Bob Hunt. Hunt said he thought that Bonjovi and
Thomas were probably being too cautious. Afterall,
the second gusher last year had occurred long after the spring melt so the
connection to the spring melt isn't obvious. But at the same time, he cannot
rule out the possibility that Bonjovi and Thomas
might be right.
McCloy has also considered calling his boss, The Sandhogs CEO.
But he thinks that wouldn't be the smartest phone call he ever made. All the
dignitaries involved in the press conference, including the CEO, are already en
route to the construction site. With the television crews already setting up,
there would be no way to mask a cancellation and he would have to give a very
convincing explanation. The project is already close to breakeven. If he halts
construction until the spring melt ends, The Sandhogs would lose over a $1
million a day, not counting interest costs. He figures that shutting down would
most likely be his last decision as a construction superintendent.
Should McCloy
call off the press conference inside the tunnel and shut down construction
until after the spring melt?
Created by Bill Starbuck 10/97